This research concludes that the manual process for determining the number of
Duplex and PET material orders causes a high cycle time of 25,761 seconds or 429
minutes. High cycle time may affect other departments, if the order is late, it will
cause Logistics department and Production department to delay due to not being
able to manufacture products on time. After the current system problems are
identified, the proposed system uses the System Development Life Cycle (SDLC)
methodology with VBA Macro as the main tool. The new system is implemented
to reduce manual process and cycle time can be reduced to achieve the aim of this
research. Implementing this new system reduces the manual process for
determining the number of quantity orders for Duplex and PEt materials to 481.1
seconds or 8 minutes.
This is a very drastic change because some of the waiting work has been taken over
by the material planner. and this gives full rights to the material to the material
planner.